Rajasthan-RERA registers 280 new projects in first half of 2022

The Rajasthan Real Estate Regulatory Authority (Raj- RERA) has registered 280 new projects in the first half of 2022 which is 89% increase in new project registration in comparison to 2021 (January to July).

About 58% of these applications belong to state capital Jaipur and remaining belong to other urban areas of the state. In first half of the 2021, total of 148 applications for registration of projects were received. This year, so far, the Raj-RERA has registered 280 projects.

An official said, “Majority of projects registered 82% are residential including plotting. As demand for the independent houses has increased after Covid-19, the industry is witnessing a steady growth.”

Kota, Udaipur, Alwar and Jodhpur are other top cities in new project registration. Apart from these, applications to register projects were received from Sriganganagar, Sikar, Chittorgarh, Ajmer, Barmer and other part of the state.

“Registration of projects from smaller cities indicates upward trend of group housing and rising impact of real estate regulation among promoters,” added official.

As per the rule, the developers under the mandatory provision of RERA Act 2016 have to register ongoing projects, which are being construction on land up to or more than 500 square metres and total number of units are eight or above.

The promoters are required to make an application to the authority for registration. Raj-RERA reviews the projects and issues necessary guidelines to promoters to ensure time- bound construction in the interest of home buyers. Once the approved information is uploaded on the website, it is not possible to change the original plan without prior approval of the RERA.

A RERA official said, “Under RERA Act, it is mandatory for the promoters to register their real estate project to sell, advertise, market, book or purchase. As consumers and builders are aware about the fact, more registrations are happening. Now, buyers refuse to buy projects without RERA registration. In past, the authority also issued notices to the developers who were violating the norms.”

Source: https://timesofindia.indiatimes.com/city/jaipur/raj-rera-registers-280-new-projects-in-first-half-of-2022/articleshow/93260070.cms

In an unprecedented development, the adjudicating authority of RERA detained a builder under civil prison for 15 days for alleged wilful disobedience.

Developer Who Violated Order Held For 15 Days

In an unprecedented development, the adjudicating authority of RERA detained a builder under civil prison for 15 days for alleged wilful disobedience. The man’s health deteriorated from the shock after which he had to be admitted to a private hospital in Gandhinagar. The builder was taken into the custody by RERA officials and kept in the office in Gandhinagar overnight after he was allegedly found guilty of disobedience.

RERA’s adjudicating authority P R Patel took the stringent action after he found irregularity and that the regulator had granted injunction on sale of seven bungalows built under a scheme called Kedarnath Bungalows, developed by Rajesh Motiyani and his partners in the firm Rameshwar Developers. The authority has also issued notices to the three partners Anil Gidhawani, Anil Vidhani and Kamlesh Makhija.
As per the case details, the firm had purchased land from Ozon Developers for a consideration of Rs 9.15 crore by registering a sale deed on October 21, 2015. The applicants, Ashish Tekwani and others, purchased seven bungalows in the scheme in 2016-17 and paid earnest money to the firm. The project application was pending and the scheme also remained uncompleted. The applicants later filed a complaint before RERA in 2019 over the issue.

During the proceedings, Motiyani declared before the authority that he had no objection if the interim or final injunction would be granted against transfer of the bungalows. He had also declared that he was reconstituting the partnership firm and preparing necessary documents for registration before RERA. The three partners remained absent in the proceedings. On September 12, 2019, RERA passed an order in favour of the applicants and directed the builder to complete the remaining work within six months and hand over possession to them. It was also directed not to sell the seven bungalows or transfer the scheme to anybody else without taking consent of the allottees. The order was not challenged in any higher forum and hence it attained finality.

When the builder didn’t comply with the order issued by RERA and didn’t give the possession, the complainant filed Execution Proceedings under section 40 of Gujarat RERA Act on March 17, 2021. During the hearing, the builder assured that construction would be completed and the approval of the project would be taken from RERA.

Later, the builder sold the land with all 12 bungalows to one Arjun Khilwani for a consideration of Rs 3.74 crore through a registered sale deed at Naroda sub-registrar office without obtaining prior approval from RERA. The sub-registrar registered the property though the order issued by RERA on September 12, 2019 was conveyed to his office. The authority sought explanation, but he couldn’t give any and he was taken into civil custody for 15 days for wilful disobedience on Monday.

Meanwhile, the court issued show cause notice to the sub-registrar of Naroda ward, Praful Modi, for registering the property despite an injunction granted by RERA over selling or transferring bungalows booked by a complainant. As per RERA law experts, this is the first time such a situation has arisen.

Source: https://www.ahmedabadmirror.com/rera-adjudicator-cracks-the-whip/81840478.html

RERA, Gurugram, has directed the builders to refund homebuyers money in 90 days along with 9.70 % interest following their failure to give possession of apartments and plots in a stipulated time period.

RERA orders 23 builders to refund money to 63 buyers

The Real Estate Regulatory Authority (RERA), Gurugram, has directed the builders to refund homebuyers money in 90 days along with 9.70 % interest following their failure to give possession of apartments and plots in a stipulated time period.

The RERA orders have come in the wake of multiple complaints from the Gurugram-based homebuyers who after losing their hopes to have their units had petitioned RERA seeking a refund of the amount they had paid to builders.

“The authority has ordered to refund deposited amounts to homebuyers after hearing both the parties (builders and allottee) and on finding builders guilty for non-delivery of units as per builder buyer agreements. The builders should not take homebuyers for granted,” KK Khandelwal, RERA chairman, said in a release.

“The builders failed to complete the projects and deliver the promised units to homebuyers within stipulated time even after collecting good initial amounts,” said Khandelwal.

He said in July alone nearly 300 matters were listed before the authority for adjudication. In the 63 cases, the authority adjudicated the matter allowing a refund with interest at the rate of 9.70%. These adjudications pertain to 17 builders and the refund amount is close to ₹50 crore.

The authority has said in case the builders don’t follow the order, the complainant can approach the adjudicating authority for execution of orders.

In another 15 matters, the authority has ordered a refund after a deduction of 10% earnest money. In all 300 matters, the homebuyers largely wanted a refund and that shows the callous attitude of promoters, the authority has observed.

Khandelwal said the authority gets hundreds of complaints on a daily basis in which mostly buyers want a refund or delayed interest.

Source: https://www.hindustantimes.com/cities/chandigarh-news/rera-orders-23-builders-to-refund-money-to-63-buyers-101658442377351.html

State government seeks Odisha RERA help to bring changes to real estate rules

The State government has sought recommendations from the Odisha Real Estate Regulatory Authority (ORERA) to bring necessary modifications to the agreement for sale provision under Odisha Real Estate (Regulation and Development) Rules-2017 in conformity with the RERA Act and its rules.

The government move comes following the order of the Orissa High Court in this regard on June 22. As per the HC order, the State government will also re-examine and bring necessary changes to the format of the ‘agreement of sale’ in the rules in line with the RERA act.

Accordingly, the Housing and Urban Development department has sought recommendations from ORERA in this regard. Sources said necessary amendments are required to remove the difficulties in the existing ‘agreement to sell’ provision prescribed in the ORE (R&D) Rules 2017 which has led to non-registration of the sale agreement by the Inspector General of Registration (IGR).

RERA activists said no clause in the agreement to sale should allow any part of the ‘common area’ to be with builder or even booked or sold to individual buyer as the entire land as well as common area of a project is required to be registered in the name of the ‘Association of Allottees’ formed under the Act.

The agreement to sell also must clearly mention the ‘saleability of Covered Parking’, a tabular format for price breakup, cost of the land, share of land and common areas as well as transaction relating to carpet area.

Source: https://www.newindianexpress.com/states/odisha/2022/jul/13/state-government-seeks-odisha-rera-help-to-bring-changes-to-real-estate-rules-2476037.html

MahaRERA standardises home allotment letters for realtors

The Maharashtra Real Estate Regulatory Authority (MahaRERA) has introduced standardised allotment letters for developers in a bid to bring in transparency and minimise buyer-seller disputes.

The newly introduced allotment letter would require developers to mention the date of handing over the possession of the booked property, percentage of charges levied on cancellation of booking, parking allotment and other details.

MahaRERA officials said that a standard allotment letter has been readied in a bid to bring in uniformity and safeguard the interest of flat buyers and developers.

The allotment letter prescribes the minimum period within which the booking can be cancelled and the upper limit of the percentage of the amount to be deducted in case an allottee desires to cancel the booking.

“The promoter may increase the number of days within which the booking can be cancelled as well as decrease the percentage of the amount to be deducted in the event of cancellation of the booking,” the letter stated.

Developers need to upload the allotment letter or the amended form of allotment letter at the time of applying for registration of the real estate project, said officials.

In case of non-compliance of the same, the application for registration of the project shall be liable to be rejected.

All MahaRERA developers would have to follow the model allotment letter or face action, stated consumer activists.

There is a provision in the MahaRERA that if a developer fails to follow the notification circular, then the real estate authority could slap a fine up to 5% of the project cost.

The same would be applicable to developers in the event of their not accepting the model allotment letter format, said Ramesh Prabhu, activist and chairman of the Maharashtra Societies Welfare Association.

Earlier, there used to be no mention of the cost of a flat in the allotment letter, but now, as per the model allotment letter, the builder has to mention the value of the property. According to the model allotment letter, in case of cancellation of a flat booking after 60 days, a developer can only charge a maximum of 2% of the cost of a flat as forfeiture fees.

Advocate Manjunath Kakkalameli told TOI that the standardised allotment letter would save flat buyers from legal loopholes. “Earlier, there were some issues with allotment letters as they did not meet the provisions and rules of MahaRERA and buyers had a trying time getting possession of their flats. This model letter will bring in transparency and help in reducing legal hurdles,” he said.

Some builders have expressed concern that small developers may avoid MahaRERA registration. “While big builders in metro cities will abide by the rules, developers in smaller cities and districts may not adhere to the model allotment letter,” said a leading builder in the state.

Source: http://timesofindia.indiatimes.com/articleshow/92626283.cms

The validity of MahaRERA registration of over 4,500 real estate projects in the state with more than 3,50,000 flats has lapsed, as per the official MahaRERA website.

MahaRERA registration of over 4,500 real estate projects in state lapsed

The validity of MahaRERA registration of over 4,500 real estate projects in the state with more than 3,50,000 flats has lapsed, as per the official MahaRERA website. However, there is no mechanism in place to check if these projects are continued to be marketed, despite promoters being barred from selling the flats. In view of this, experts have called for a special vigilance cell.

Advocate Godfrey Pimenta, who practises in MahaRERA, said, “As per MahaRERA, in the past 5 years, 36,000-odd real estate projects were registered and the registration of about 4,500 or 12 per cent of the projects have lapsed. It is estimated that around Rs 80,000 crore is stuck in such projects.”

Association of Allottees

“In RERA, there’s a provision for takeover of stalled projects by Association of Allottees or flat buyers. Last week, retired IAS officer Sanjay Deshmukh was appointed to lead a team of experts to guide on solutions to revive the stalled projects. It would be advisable to refer all cases of stalled projects under Sections 7 & 8 of RERA to this particular team so that hearings get priority. Secondly, some mechanism, such as a vigilance cell, should be in place, otherwise developers will continue to sell flats at such lapsed projects to unsuspecting buyers. Thirdly, the team under Deshmukh will need legal sanctity to enforce recommended solutions,” Pimenta added.

CA Ramesh Prabhu, founder of MahaSEWA, said, “Though it is a requirement of RERA for promoters to facilitate registration of Association of Allottees on booking of more than 50 per cent flats, only few promoters take such initiatives. And even if allottees want to register the association, the list of allottees is not made available by the promoters under the confidentiality of data. Thus, the association of allottees becomes a non-starter.”

“The order of MahaRERA regarding Revival of stalled projects requires that more than 50 per cent of allottees in the projects should register an Association of allottees and file an application under section 7 and 8 of RERA to take over the project for completing the balance work. So far, we have not seen any proactive steps initiated by MahaRERA. We have recently known that Sanjay Deshmukh, a retired IAS officer, has been engaged by MahaRERA to initiate necessary steps to revive and complete the stalled projects. This is a welcome move,” said Prabhu.

Lapsed Projects

Advocate Vinod Sampat, founder and president of Flat Users Residents Welfare Association, said, “One sector where MahaRERA intervention is urgently required is lapsing of real estate projects. To a certain extent, the problem can be sorted out by appointing a special vigilance cell with powers to regularly scrutinise complaints pertaining to lapsed projects. The need of the hour is to install an element of fear in the minds of builders.”

Advocate Nilesh Gala from Practitioners Welfare Association said, “As per the circular issued by MahaRERA, if the validity of the registration expires then the promoter will not be able to register any Agreement for Sale as the sub-registrar has to check the validity of the certificate issued by MahaRERA for the project.” Estimated amount stuck in such projects is around ₹ 80k cr.

Source: https://www.mid-day.com/mumbai/mumbai-news/article/maharera-registration-of-over-4500-real-estate-projects-in-state-lapsed-23233356

UP-Rera cancels Registration of 3 Ghaziabad Projects

The UP Real Estate Regulatory Authority (UP-Rera) this week cancelled the registrations of three real estate projects in Pratap Nagar area of the city after it found that the builder was unlikely to complete the construction in the stipulated time and had not followed some other norms.

About 1120 flats in 1504 housing units across the three projects — Antriksh Sanskriti Phase-2, Antriksh Sanskriti Phase-3 and Raksha Vigyaan Sanskriti Phase-2 — had been booked so far.

The Authority took the decision after complaints by several homebuyers, who alleged a delay in construction and said the builder had failed to deliver their houses despite several extensions in deadline.

“Under the powers of the UP-Rera Act, the builder has been declared a defaulter and this has been conveyed to Rera offices of other states and Union territories,” an Authority official said on Wednesday.

“It has been decided by the Authority to freeze the bank accounts linked to the projects to block any transactions. The builder’s access to the UP-Rera website has also been restricted,” the official added.

The Authority has now created a project advisory and monitoring committee – comprising officials of UP-Rera and the Ghaziabad Development Authority (GDA) — to complete the construction.

“The committee will work on a plan to complete the unfinished projects in the larger interest of homebuyers” the official cited above said.

Work on the three projects began in 2015, and was to be completed by July 2022 (both Antriksh Sanskriti projects) and June 2023 (Raksha Vigyaan Sanskriti). “But an onsite inspection found that the builder, under no circumstances, would be able to complete the remaining construction and development work,” the official added. Construction work had been completed around 30-40% in the Antriksh projects and it hadn’t even begun in the third project.

For Raksha Vigyaan Sanskriti Phase-2 project, land was provided to the developer to build the flats; of these, 32% are to be owned by a cooperative society, according to a homebuyer.

Other homebuyers said the builder had promised to deliver the flats years ago. “I had booked a 2BHK but the builder failed to hand it over and kept extending the deadline. It’s now that the UP-Rera has taken action against the builder,” said Sandeep Singh.

Source: https://timesofindia.indiatimes.com/city/ghaziabad/up-rera-cancels-registration-of-3-ghaziabad-projects/articleshow/92400117.cms

Haryana RERA orders Forensic Audit of 5 Affordable Housing Projects

The Haryana Real Estate Regulatory Authority (H-Rera) has ordered forensic audits of all five affordable housing projects by developer Mahira Group in sectors 63, 68, 95, 103 and 104.

The move comes after reports on alleged gross irregularities by the developer in procuring licences for these projects.

The department of town and country planning (DTCP) blacklisted the company, its directors and shareholders last month.

According to a DTCP order, the developer fabricated bank guarantees and forged signatures of bank officials on the documents submitted to the department for procuring the licences of its affordable housing projects.

Now, H-Rera has appointed an executive monitoring engineer to conduct the probe and directed Mahira to submit documents.

In an order, KK Khandelwal, the chief of the Gurugram H-Rera bench, said his officials visited the sites of these projects and submitted a report about their progress and the physical status of construction.

The report claimed that the construction at site doesn’t seem commensurate with the payments collected from buyers and the developer didn’t submit quarterly progress reports of the projects as well.

Taking action on the complaints, the authority directed the company to furnish details including total amount collected from allottees so far, work done on site, bank accounts where the payments were received, withdrawal from the accounts and annual audit reports of last two financial years within seven days (June 6).

The replies submitted by the developer, however, were found to be not in order, so H-Rera on May 28 restrained the promoter from withdrawing from the project account and from creating any third-party rights by way of mortgage/loan.

“The authority further ordered forensic audit of the project account and fixed audit fees of Rs 50,000 to be paid by the developer and appointed Rera executive monitoring engineer JS Sindhu for conducting the enquiry. The authority further directed the developer to produce books of accounts and documents related to loans, funds diverted to other accounts, allotment of units, amount collected from the allottees from sale of units and other related documents required by the enquiry officer,” said an official. Despite efforts by TOI, the developer could not be reached and its office did not respond to calls and messages.

Source: https://timesofindia.indiatimes.com/city/gurgaon/haryana-rera-orders-forensic-audit-of-5-affordable-housing-projects/articleshow/92242191.cms?from=mdr

Five years of MahaRERA: Authority issues recovery warrants for over ₹ 717 crore against developers, disposes of more than 11,000 complaints

Five years since the Maharashtra Real Estate Regulatory Authority (MahaRERA) came into existence in the country’s financial capital, it has received 17,061 complaints against developers, of which it has disposed of 11,287. Of these, more than 50% of the complaints are by homebuyers in the Mumbai Metropolitan Region, MahaRERA chairman Ajoy Mehta tells Moneycontrol’s Mehul R Thakkar. Edited excerpts:

What has been the Authority’s role with regard to enforcement of MahaRERA orders? What is the Authority doing to address the issue?

RERA has three distinct roles, of which the first is that of regulatory oversight, which touches the question of enforcement. Second role is adjudication where a dispute has arisen between the flat buyer, promoter or the plot buyer, followed by overall housing policy…We are bringing in a lot of things to ensure that regulatory oversight is strengthened. The fundamental principle that I am following in strengthening regulatory oversight is transparency. This is because I personally, strongly feel that once a flat buyer and flat seller has an equal amount of information, that is when the buyer will make a correct decision. So we are revamping the regulatory oversight process to ensure all information comes out in the public domain. Once we implement the law correctly, litigation will automatically stop. We need to ensure that the compliances are done properly by promoters.

Are redeveloped/under-redevelopment projects covered under MahaRERA? What is the authority doing to address the problem of projects under redevelopment?

As far as the RERA Act is concerned, it is very clear that those that are under redevelopment are not covered under the Act. But, of course, the sale component of the redevelopment is covered under the RERA Act wherever money is involved. However, where something is given in lieu of something you owned is not covered under RERA. This is what the Act says and as an authority we are the interpreters of the Act…The question of what we are doing to address the problem of projects under redevelopment is best addressed to the government because they are the lawmakers.

How many complaints have been filed in the last five years and how many cases disposed of? What percentage of cases is from the Mumbai Metropolitan Region (MMR), Pune, etc? Which area has witnessed the maximum number of complaints?

A majority of the complaints are from Mumbai or Mumbai Metropolitan Region (MMR). This is followed by Pune… However, now we are putting a lot of things in place so that these complaints come down. Much more than 50% complaints are from Mumbai, but if you see that predominantly they are pre RERA-project complaints, which have now got carried on. Post-RERA, we are not finding much of this happening. As of May 24, 2022, we have around 5,000 complaints pending. We have disposed of more than 11,000 complaints out of the more than 17,000 complaints that we have received till now.

Has the Conciliation Forum formed under the Real Estate (Regulation and Development) Act, 2016 (RERA) and MahaRERA to facilitate dispute settlement between homebuyers and developers benefited buyers? How many cases have been settled over the last few years/ last one year?
The good thing is that this conciliation forum has been very beneficial for buyers. In the first hearing, when the homebuyers come to us, we ask them if they want to go in for conciliation…In the forum, once the buyers get favourable results and consent terms are signed, the matters are resolved very fast. Whereas when we pass an order, one side is happy and the other side is not, which leads to appeals and more litigation So, we are trying to encourage the Conciliation Forum in a big way. Now, we find that nearly more than 60% of the complainants are preferring reconciliation and the success rate of the forum is also very good. Also, we have told people that you go for reconciliation, and if you do not succeed your case is still with us. We are not throwing out their case and they remain in the queue. But while they are in the queue, we tell them to try reconciliation. If you succeed, it is a win-win situation for both the parties… This is resulting in 60% of complaints getting settled in the Conciliation Forum within 90 days.

Have promoters and homebuyers reached settlements in respect of recovery certificates? What does this amount to?

In the last five years, we have issued 751 recovery warrants against developers of around Rs 717 crore. Let me tell you that in following the issuance of recovery certificates, there is a process to be followed before and after. Sometimes people feel that once a RERA order is issued, things will work out immediately. But there is a process to be followed wherein suppose we pass an order saying ‘refund the money’ but the promoter does not refund the money. Later, what we do is we issue a revenue recovery certificate (RRC) to the tehsildar, saying ‘please take this property of X and sell it off and give the money to say Y.’ The minute the RRC goes to the tehsildar, he cannot say now this property is taken over. He has to examine the title of the property. Maybe someone else is the part-owner, and the whole process is followed. These processes take time and they reach a conclusion. However, once you have got the order of RERA in your favour, the wheels of justice have started moving. It will take time but it will reach its destination.

Should the RERA Act be amended to make financial institutions accountable for the completion of projects backed by them?

I will refrain from commenting on where what needs to be amended. This is because I clearly know what my role is, and I am not the lawmaker. It will be very incorrect for me to say what should be amended or what should not be. But only one thing which I tell everyone is please remember RERA is a very young law as compared to others and is just five years old. There are lots of ideas and I feel let us all not rush to the conclusion that my idea is the best idea. This is because when you amend the law, please understand that any law which is amended must stand the test of time. The amendment should stand because we cannot get up tomorrow and say that this amendment is wrong, and we again should do an amendment. More and more we amend a law, it is not a good sign, and it dilutes or does not serve the purpose that you wanted it to serve. But what I am saying is that every law needs to grow, expand, but give it time and thought. Let us not just jump to conclusions because it is a very infant law. Until last year, all the hearings were of pre-RERA (cases), and it is only now that things are taking shape.

There have been allegations that the orders or directions issued by RERA are not complied with by the promoters, and consumers are left to go to the court.

Once you have a RERA order in your favour, something has already started, and it takes time. It takes time because the process of justice takes time. But justice is given and the way we are giving it is by the Conciliation Forum.

What is the pendency rate? How much time does it take to complete a hearing and passing an order in one particular case?

We are having a pendency of 5,000 cases. Until now, we were hearing cases of 2019, and now we have started hearing cases of 2020. Once the first hearing is taken, we are ensuring that we pass an order in, say, three to four months. We are working on ensuring we do not give too much time for simple submission of reply or documents.

What is the one thing that you want to change when it comes to MahaRERA? What is your message to the homebuyers and developers?

My message to buyers is to try out the Conciliation Forum and not to straight away jump into disputes or litigation. If not, please come to us, we are there to give you justice. The homebuyers should make themselves aware of everything, but we also realise that buyers do not have experience. Hence, it is also for us to tell them for which we are trying to put a lot of information in the public domain. We are now also making a standard sale agreement, a standard allotment letter, and they should read that, and make a proper decision. To promoters my message is very clear that they need to put all the information out in the public domain very transparently. They need to understand the risk of the project because every risk converts into time and money. If the project has zero risk, it will certainly get completed on time. Promoters need to see risks and they are supposed to give timelines accordingly. Build in your costs and risks properly into the project and later inform the client… The promoter has all the information about the project, and we are now working (to ensure) that things should come out very transparently and in simple language. We are ensuring we monitor projects continuously. Regulatory oversight is very important for there being no litigation, and for this we need to have improved scrutiny.

Source: https://www.moneycontrol.com/news/india/coronavirus-update-daily-covid-19-positivity-rate-over-3-8676991.html

The Tamil Nadu Real Estate Regulatory Authority has ordered Ozone Projects, a developer, to pay a refund of Rs 1.7 crore to one of the company's clients with an interest of 9.3 per cent.

Tamil Nadu RERA asks realtor to pay buyer Rs 1.7-crore flat cost with 9.3 per cent interest

The Tamil Nadu Real Estate Regulatory Authority (TNRERA) has ordered Ozone Projects, a developer, to pay a refund of Rs 1.7 crore to one of the company’s clients with an interest of 9.3 per cent from date of complaint for failing to honour a 2011 agreement between the two on handing over the flat.

The complainant, Aley Cherian, had paid the amount to acquire a 3 BHK apartment at a residential complex in Metrozone, one of the developer’s luxury housing projects in Chennai.

However, Ozone did not hand over the flat to him as agreed in June 2014. As Cherian’s calls to the developer asking for a refund over the last eight years did not bear fruit, he finally filed a complaint to the TNRERA for intervention on April 8, 2021.

Sunil Kumar, a single-member bench of the TNRERA, after listening to the arguments of Cherian, represented by practising company secretaries K Gaurav Kumar and Alpha Jain asked the developer to refund the amount within 30 days by paying an interest rate of 9.30 per cent on the amount starting from the date of filing of the complaint to TNRERA.

Sunil Kumar, in his order, also said that Cherian is at liberty to move the adjudicating officer for claiming compensation. Similarly, the charge of the aforesaid amount as encumbrance shall be on the flat booked by Cherian till repayment of the claim as per the order.

Sunil Kumar also ordered the office of TNRERA to intimate the encumbrance created by the charge in the order to the sub-registrar concerned. Upon the repayment of the claim as per the order, Cherian shall execute the cancellation of the construction agreement and sale deed as the case may be at the expense of Ozone Projects, Sunil Kumar added. Rs 15 per sq ft was assured for a month’s delay.

The total cost of the apartment in the AB Tower of the complex was 1.92 crore. In November 2011, during the construction agreement, a sale deed was executed for Rs 22.56 lakh and Rs 1.70 crore was paid. The remaining amount was to be paid at the time of handing over the apartment.

In the event of a delay, the developer had agreed to pay a sum of Rs 15 per square feet per month till the resolution unit was handed over. The agreement stipulates that if the delay exceeds more than six months, the builder shall pay an interest of 10 per cent per annum for further periods of such delays.

Though the agreement was signed, it was not registered as the construction agreement stipulates the execution of the sale deed only on the completion of 80 per cent of construction, which did not happen.

During the hearing, Ozone Projects agreed that Cherian was entitled to seek a refund but it sought time. Sunil Kumar said that as per Rule 18 of TNRERA rules, the rate of interest payable shall be the highest marginal cost of lending rate of interest of SBI (7.30 per cent) plus 2 per cent per annum.

Source: https://www.newindianexpress.com/states/tamil-nadu/2022/jun/02/tamil-nadu-rera-asks-realtor-to-pay-buyer-rs-17-crore-flat-cost-with-93-per-cent-interest-2460769.html/a>